N2 - Ring distribution network system has a complex problem. Besides that, the addition of distributed generators (Distributed Generation) would make the changes in network topology configurations and affected the value of short-circuit current that supply the load on each relay. The difficulty to define the setting of relay operation setting that localize the fault would be increase. From these problems, it requires a method to reduce the complexity of coordination protection in ring distribution system with zone selective interlocking method which is modelled and adapted by using artificial neural network. In this paper, adaptive methods would be used to localize the short circuit which is faster than the manual method (conventional). The output of the system is locating the short circuit current and the operation system relay which is modelled by a status system. The status can produce a relay setting that capable in every configuration on the system.
AB - Ring distribution network system has a complex problem. Besides that, the addition of distributed generators (Distributed Generation) would make the changes in network topology configurations and affected the value of short-circuit current that supply the load on each relay. The difficulty to define the setting of relay operation setting that localize the fault would be increase. From these problems, it requires a method to reduce the complexity of coordination protection in ring distribution system with zone selective interlocking method which is modelled and adapted by using artificial neural network. In this paper, adaptive methods would be used to localize the short circuit which is faster than the manual method (conventional). The output of the system is locating the short circuit current and the operation system relay which is modelled by a status system. The status can produce a relay setting that capable in every configuration on the system.
KW - Artificial Neural Network
KW - Network Distribution System Ring
KW - Zone Selective Interlocking
UR - http://www.scopus.com/inward/record.url?scp=85050404559&partnerID=8YFLogxK
U2 - 10.1109/ICOIACT.2018.8350817
DO - 10.1109/ICOIACT.2018.8350817
M3 - Conference contribution
AN - SCOPUS:85050404559
T3 - 2018 International Conference on Information and Communications Technology, ICOIACT 2018
SP - 196
EP - 201
BT - 2018 International Conference on Information and Communications Technology, ICOIACT 2018
PB - Institute of Electrical and Electronics Engineers Inc.
T2 - 1st International Conference on Information and Communications Technology, ICOIACT 2018
Y2 - 6 March 2018 through 7 March 2018
ER -