Abstract

Reliability is a critical aspect of planning and operational control in the Java-Madura-Bali (JAMALI) power system, particularly under N-1 contingency conditions that may cause load flow imbalances, equipment overloads, and cascading blackouts. The Krian subsystem, a strategic node in the JAMALI power system, currently experiences N-1 reliability issues in the Krian-Mojokerto Subsystem. To improve reliability, a sixth 500 MVA Interbus Transformer (IBT) is scheduled for installation in 2025, resulting in two alternative operating schemes: two-subsystem and threesubsystem splitting. This paper evaluates six IBT operation strategies using Failure Mode and Effects Analysis (FMEA) method supported by power flow and short-circuit simulations. The results indicate that the two-subsystem splitting scheme achieves a lower Risk Priority Number (RPN) and satisfies the N-1 criterion, thereby improving the reliability of the Krian-Mojokerto Subsystem. Although the short-circuit current at the 150 kV Krian Substation increases from 23.77 kA to 28.33 kA, it remains within the circuit breaker interrupting capability. In contrast, the three-subsystem splitting scheme fails to satisfy the N-1 criterion and introduces a potential 275 MW Stage-3 Overload Shedding (OLS) risk, despite reducing the shortcircuit current to 18.08 kA. The study contributes a risk-based evaluation framework, with novelty in integrating contingency analysis and FMEA for subsystem reconfiguration. These findings support the two-subsystem splitting operation as the recommended operational strategy for the new Krian Subsystem.

Original languageEnglish
Title of host publication27th International Seminar on Intelligent Technology and Its Applications, ISITIA 2026
PublisherInstitute of Electrical and Electronics Engineers Inc.
Pages1049-1054
Number of pages6
ISBN (Electronic)9798319521576
DOIs
Publication statusPublished - 2026
Event27th International Seminar on Intelligent Technology and Its Applications, ISITIA 2026 - Hybrid, Bali, Indonesia
Duration: 22 Jul 2026 → 24 Jul 2026

Conference

Conference27th International Seminar on Intelligent Technology and Its Applications, ISITIA 2026
Country/TerritoryIndonesia
CityHybrid, Bali
Period22/07/26 → 24/07/26

UN SDGs

This output contributes to the following UN Sustainable Development Goals (SDGs)

  1. SDG 7 - Affordable and Clean Energy
    SDG 7 Affordable and Clean Energy

Keywords

  • FMEA
  • N-1 contingency analysis
  • configuration optimization
  • load flow
  • subsystem reliability